Which documents required to get a Licence from Ministry of Environment (MoE) for a manufacturing unit/factory ?

  • Prescribed Form-Duly filled in & signed (with IEE check list)

  • Local (factory) Trade Licence -copy

  • TIN

  • Company Memorandum & Articles of Associations

  • Bank Solvency Certificate

  • Photos

  • Land deed, documents copy or Rent deed copy

  • Meeting Resolution of local neighbor, persons and citizens 

  • NOC from local Union Parishad/authority

  • Project Profile

  • Prescribed fees

  • Layout plan (both site & plant)

  • ETP-layout plan & description (if required)

  • Location map of the project

  • Process Flow Diagram

  • Drainage use- Layout plan

  • Board of Investment (BOI) registration copy

  • Note :  All documents must be certified by MD. List may vary case to case.